For the upcoming
week of January 12, 2004, the following construction activities
will take place:
- Vinyl floor
tile installation level D.
- Ceramic
Tile installation - Bathrooms.
- Ceiling
Grid installation.
- D Level
Millwork (clinic unit casework) arrival and installation.
- Rolling
counter top doors - D and B Level reception desks.
- Curtainwall
and Glass installation.
- Sheetrock
and taping 'D' level.
- Painting
- Door frames.
- Metal Panel
installation continuing.