For the upcoming
week of February 3, 2003, the following construction activities
will take place:
- Continue
development of concrete wall along 12th Street
- Complete
soil retention and excavation adjacent to current building.
- Removal
of operatory mock-ups from B842. The Amcase mock-up, which was
selected for the new clinics, will be moved to the D-Level,
Group B area in the next week. The mock-up will be installed
to permit continued development of the operatory, to include
placement of accessories, sink and faucet selection, etc.
- I have
requested more frequent changes to the filter material covering
the air intakes along 12th. By the end of this week, heavy machinery
use directly beneath the intakes will be completed, as the soil
retention and excavation adjacent to the current building are
completed. As our construction project progresses, NJDS and
EOHSS will continue to monitor this situation and ensure that
the entrance of odors into the building are kept to a minimum.
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School
History
of Previous Weekly Activities
Previous
Page
|