For the upcoming
week of February 9, 2004, the following construction activities
will take place:
- Ceramic
Tile installation - Bathroom Floors.
- Ceiling
Grid installation and 'B' level
- D Level
Millwork installation.
- Curtainwall
mullion cover installation.
- Sheetrock
and taping 'C' and 'B' level.
- Painting
- Door frames and walls 'D' level
- Metal Panel
installation continuing.
- Louver
Installation.
- Lighting
installation 'D' and 'B' levels
- Grills
and diffuser installation 'D' and 'B' levels
- Sprinkler
head installation 'B' level
- Operatory
casework and accessory installation 'D' level
- Exterior
rail installation
- Sunshade
Installation
- Operatory
plumbing and electrical hook-ups
- IST cabling
- VCT 'D'
level admin areas
- Stairwell
framing.
- Removal
Exterior temp partition 'B' level
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Office of Academic Affairs, New Jersey Dental School