For the upcoming week of March 8, 2004, the following construction activities will take place:

  • Ceiling tile installation 'D' level
  • Painting - Door frames and walls 'D', 'C' and 'B' level
  • Metal Panel installation continuing
  • Lighting installation 'B' level
  • Grills and diffuser installation 'B' level
  • Operatory accessory installation 'D' level
  • Operatory IST hook up . IST cabling
  • Ceramic Tile installation 'B' level
  • Sliding door installation at entrance
  • Stairwell framing and sheetrock (east stair)
  • Taping and painting east stair
  • Tie-in roofing
  • Paver installation - west plaza
  • Sidewalk completion west plaza
  • West stair rail installation
  • Topsoil installation - completion
  • Door and hardware installation 'D' and 'B' levels
  • Fire Alarm tie-ins to panel / F. A. Test
  • Emergency generator test
  • Balancing
  • Equipment training

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2004 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, March 15, 2004

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel