NJDS Home Students Patients Research Calendars/Events
NJDS Home Background
Departments Curriculum Administration Honor Societies Alumni Continuing Education Admissions Additional Links Search Contact Us
OVERVIEW
WEEKLY NEWS AND RECENT PICTURES
PHASE I
PHASE II
PHASE III
IMAGES

For the upcoming week of May 5, 2003, the following construction activities will take place:

The "Topping Off" beam will be lowered this week from the top of the addition. It will be brought into the building and located on the B-level. Anyone who would still like to sign the beam can do so - it will be in the hallway for a couple of weeks.

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2002 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, May 5, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel