For the upcoming
week of July 21, 2003, the following construction activities will
take place:
- HTHW and
CHW piping in courtyard and manhole.
- Backfilling
foundation wall.
- Piping
levels 'A', 'C', and 'D'
- Ductwork
level 'A'
- Wiring
'B' level and 'D' level.
- GFRC panel
installation - as you can all see, the 12th street side is currently
being installed.
- Sprinkler
piping 'C' and 'D' level