For the upcoming week of July 28, 2003, the following construction activities will take place:

  • HTHW and CHW piping in courtyard and manhole.
  • Backfilling of trench in courtyard.
  • Piping levels 'A', 'C', and 'D'
  • Ductwork level 'A'
  • Wiring 'A' level and 'D' level.
  • GFRC panel installation.
  • Sprinkler piping 'C' level.
  • Utility tie in on 12th Avenue.

Also, this past Friday, Dr. Feldman and members of the Steering Committee were taken on a tour of the construction. Please take a look at the pictures taken by Rich Merkel to get an "inside look" at the progress of the construction.

"An Inside Look at the Progress of the Construction"

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2003 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, July 28, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel