For the upcoming
week of July 28, 2003, the following construction activities will
take place:
- HTHW and
CHW piping in courtyard and manhole.
- Backfilling
of trench in courtyard.
- Piping
levels 'A', 'C', and 'D'
- Ductwork
level 'A'
- Wiring
'A' level and 'D' level.
- GFRC panel
installation.
- Sprinkler
piping 'C' level.
- Utility
tie in on 12th Avenue.