For the upcoming
week of August 18, 2003, the following construction activities will
take place:
- Installing
pavers in courtyard.
- Piping
levels 'A', 'B', 'C', and 'D'
- Ductwork
level 'A'
- Wiring
'A' level and 'D' level.
- GFRC panel
installation south and east elevations.
- Sprinkler
piping 'B' level.
- Roofing.