|
For the upcoming
week of September 1, 2003, the following construction activities
will take place:
- Installing
pavers over trench area.
- Piping
level 'D', 'B' and 'A'.
- Tie-in
/ installing roof drains
- Ductwork
level 'A'
- Wiring
'D' and 'A' level and risers 'A' level.
- GFRC panel
adjustments.
- Sprinkler
piping 'B' level.
- Roofing
/ roof blocking.
- East stairwell
- stairs installation
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School
History
of Previous Weekly Activities
Previous
Page
|