For the upcoming
week of September 8, 2003, the following construction activities
will take place:
- Installing
pavers HTHW and CHW trench area.
- Piping
level 'D', 'B' and 'A'.
- Ductwork
level 'A'
- Wiring
'D' and 'A' level and risers 'A' level.
- GFRC panel
adjustments.
- Sprinkler
piping 'A' level.
- Roofing
/ roof blocking.
- Excavation
for power duct bank.
- East stairwell
- stairs installation