NJDS Home Students Patients Research Calendars/Events
NJDS Home Background
Departments Curriculum Administration Honor Societies Alumni Continuing Education Admissions Additional Links Search Contact Us
OVERVIEW
WEEKLY NEWS AND RECENT PICTURES
PHASE I
PHASE II
PHASE III
IMAGES

For the upcoming week of September 22, 2003, the following construction activities will take place:

  • Continue installing pavers - trench area.
  • Piping level 'D', 'B' and 'A'.
  • Exterior wall framing - C and D levels
  • Wiring 'D' and 'A' level and risers 'A' level.
  • Final GFRC panel adjustments.
  • Sprinkler piping 'A' level.
  • Roofing / roof blocking.
  • Elevator installation.
  • East stairwell - stairs installation
  • Exterior caulking
  • Installation of emergency generator
 
 
 
 
 
 
 
 
 

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2003 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, September 22, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel