For the upcoming week of September 29, 2003, the following construction activities will take place:

  • Installing pavers HTHW and CHW trench area
  • Piping level 'D', 'B' and 'A'
  • Miscellaneous duct work tie ins 'A' and 'D' level
  • Exterior wall framing
  • Wiring 'D' and 'A' level
  • Final GFRC panel adjustments
  • Sprinkler piping 'A' level
  • Roofing / roof blocking
  • East stair erection
  • Control Wiring 'A' level
  • Elevator Installation
  • Framing 'B' level
  • West plaza concrete work
  • Tie-in heat exchangers
  • Exterior caulking
 
 
 
 
 
 
 
 
 

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2003 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, September 29, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel