|
For the upcoming
week of September 29,
2003, the following construction activities will take place:
- Installing
pavers HTHW and CHW trench area
- Piping level
'D', 'B' and 'A'
- Miscellaneous
duct work tie ins 'A' and 'D' level
- Exterior
wall framing
- Wiring
'D' and 'A' level
- Final GFRC
panel adjustments
- Sprinkler
piping 'A' level
- Roofing
/ roof blocking
- East stair
erection
- Control
Wiring 'A' level
- Elevator
Installation
- Framing
'B' level
- West plaza
concrete work
- Tie-in
heat exchangers
- Exterior
caulking
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School
History
of Previous Weekly Activities
Previous
Page
|