For the upcoming week of October 6, 2003, the following construction activities will take place:

  • East and West Plaza concrete work
  • Piping level 'D', 'B' and 'A'
  • Miscellaneous duct work tie ins 'A' level
  • Exterior wall framing
  • Wiring 'D' and 'A' level
  • Sprinkler piping 'A' level
  • Roofing / roof blocking
  • East stair installation
  • Elevator installation
  • Framing 'B' level
  • Exterior caulking
  • Windows 'D' Level

In addition, the sidewalk between the NJDS and the DOC Parking Garage will be closed to pedestrians due to construction activity related to the NJDS Expansion Project beginning today.

The closed portion will begin at 12th Avenue and terminate at the east exit stair of the DOC Garage. DOC east exit stair will remain available during construction. Signage routing pedestrians to UMD destinations will be posted prior to the sidewalk closing.

 
 
 
 
 
 
 
 
 

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2003 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, October 6, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel