For the coming
week of October 7, 2002, the following construction activities
will take place:
Monday
– Interior gut of C-level, demolition of portico concrete and
removal of rubble.
Tuesday – Interior gut of C-level, demolition of portico concrete
and removal of rubble.
Wednesday – Installation of shoring at corner, interior gut, demolition
and removal of portico concrete.
Thursday – Saw cut at roof level, start demolition of overhang
area. (Will include use of hammering devices)
Friday – Demolition of overhang area. (Will include use of hammering
devices)
Saturday – Saw cut at C level, continued demolition of overhang.
TORCON will
be using jackhammers on Thursday and Friday to remove the interior
overhang area. Right now, the plan is to limit the use of this
equipment to the hours of 7-10 am and after 4pm into the evening,
to avoid disruption of the clinic and patient care activities.
The actual saw cutting will occur on Saturday.
Other construction
activities to occur this week include:
- Temporary
electric work on site (trailer and west side of site)
- PSE&G
Power Feed to Site (two week activity)
- Mass
Excavation
- Flag
pole removal / store (one was completed on Friday)