For the upcoming week of October 13, 2003, the following construction activities will take place:

  • East Plaza concrete work
  • Piping level 'D', 'B' and 'A'
  • Fan guard installation and filter box installation
  • Exterior wall framing
  • Exterior soffit work
  • Wiring 'D' and 'A' level
  • Emergency generator duct bank and pad work - adjacent to school and DOC parking deck
  • Sprinkler piping 'A' level
  • Roofing / roof blocking
  • Installation of main electrical gear
  • Elevator Installation
  • West plaza concrete work
  • Exterior caulking
  • Framing 'B' level
  • Windows 'D' Level
  • Temp wall existing Dental School 'C' level

For further information please contact:

Dr. Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School

History of Previous Weekly Activities

Previous Page


UMDNJ Home

All contents copyright © 2003 UMDNJ. All rights reserved.
All information within this site subject to change without notice.
Revised: Monday, October 13, 2003

[Students] [Patients] [Research] [Calendars/Events]
[Departments] [Curriculum] [Administration] [Contact Us]
[Home] [Alumni] [Continuing Education] [Additional Links] [Honor Societies]
[Search]

Please email questions and comments pertaining to the website to: Rich Merkel