For the upcoming
week of October 13, 2003, the following construction activities
will take place:
- East Plaza
concrete work
- Piping level
'D', 'B' and 'A'
- Fan guard
installation and filter box installation
- Exterior
wall framing
- Exterior
soffit work
- Wiring
'D' and 'A' level
- Emergency
generator duct bank and pad work - adjacent to school and DOC
parking deck
- Sprinkler
piping 'A' level
- Roofing
/ roof blocking
- Installation
of main electrical gear
- Elevator
Installation
- West plaza
concrete work
- Exterior
caulking
- Framing
'B' level
- Windows
'D' Level
- Temp wall
existing Dental School 'C' level