For the coming
week of November 11, 2002, the following construction activities
will take place:
- Temporary
electric work on site (Final tie - in and lighting complete)
- Verizon
pull phone lines to site (Verizon delay until 11/15)
- Soil
nailing
- Mass
Excavation
It is expected
that the excavation will be completed some time around Thanksgiving.
Please feel free to contact me if you have any questions.
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School