week of November 24, 2003, the following construction activities
will take place:
- Exterior
wall framing
- Electrical
Risers and panels levels D, B and A
- Demolition
'D' Level and 'C' Level
- Roofing
at canopy areas
- Sheetrock
and taping 'D' level and 'A' Level
- Elevator
Installation
- West plaza
steps, sidewalk concrete
- East plaza
plantings
- Exterior
caulking
- Windows
'C' level
- Curtain
wall south and east elevations
- Pavers
courtyard
- Piping
and duct insulation 'D' level
- West stair
installation