For the upcoming
week of December 2, 2002, excavation will continue. The pace of
the excavation has slowed in the past week, due to conditions
discovered adjacent to the existing building foundation. The construction
manager has modified the excavation approach in this area in order
to address the condition. Over the next week, this final area
will be excavated.
During the
next week, the excavated area will be prepared for the first delivery
of concrete, which will be poured in the dug out areas for the
addition footings. The concrete may arrive, at the earliest, by
the end of this week.
Finally,
feedback continues to be received regarding the operatory mock-ups.
Please feel free to leave your comments on the pad located in
the mock up area, or by e-mail. All comments are being collected
and shared with the steering committee. Thanks to those who have
already taken the time to give the committee their thoughts and
opinions.
For
further information please contact:
Dr.
Fotinos Panagakos - fpanagak@umdnj.edu
Associate Dean
Office of Academic Affairs, New Jersey Dental School