For the upcoming
week of December 8, 2003, the following construction activities
will take place:
- Exterior
wall framing
- Light fixture
installation level 'A'
- Demolition
'D' Level
- Demolition
'C' Level
- Sheetrock
and taping 'D' level
- Elevator
Installation
- Exterior
caulking
- Taping
sheetrock 'A' level
- Glass curtainwall
'B' level
- Curtainwall
west elevation
- Piping
and duct insulation 'A' level
- Sunshade
installation
- Landscaping